An IPA timeline (the schedule for the Swiss final apprenticeship project) needs a defined time axis, work packages in phases, milestones and a traceable planned vs actual comparison. planomatti's free IPA template sets up the calendar, grid and submission date – you enter your own work packages, and the planned vs actual comparison almost keeps itself up to date during the IPA.
¹ According to the IPA-Handbuch QV 2026 Mediamatik, Canton of Zurich. For IT, Digital Business and other cantons, the rules of your examination board apply – everything can be adjusted in planomatti.
Here's how to do it – whether with planomatti, Excel or on paper.
Take the deliverables and task packages from the detailed assignment and assign them to phases (e.g. planning, concept, implementation, quality assurance, documentation).
Set the start day, number of working days and school days. Choose a 2- or 4-hour grid – planomatti can also do 30 minutes and 1 hour.
Give each package realistic planned blocks. Schedule documentation and the work journal from the start, not just at the end.
Decision on variants, interim meeting with the expert, product finished, test upload, submission.
Record the actual time every day – in planomatti with a timer or painted straight into the grid.
Why did a package take longer or shorter? Pick a reason, add a short note – planomatti writes the sentence.
Export the whole Gantt and each day separately as SVG, PDF or PNG and place them in InDesign.
A possible framework for a Mediamatik IPA with 10 days of 8 hours – as a guide. In planomatti you start empty and enter the packages from your own assignment.
| Phase | Work packages | Planned |
|---|---|---|
| Planning & analysis | Project planning & timeline, target group & customer persona | 9 h |
| Concept | Ideas, creativity techniques, solution variants | 6 h |
| Implementation | Design, execution | 26 h |
| Quality assurance | Tests with test users, evaluation | 6 h |
| Documentation & submission | Writing the docs, layout, indexes, appendix, work journal | 29 h |
| Total (rest = buffer) | 76 h | |
– Planned/actual only as a total instead of per package and visually separated.
– Milestones without a date or without documented completion.
– Documentation only scheduled from day 8.
– Deviations without justification in the journal.
– Overtime not shown in the journal and the timeline.
– Name and date missing on exported pages.
Planned is the planned time per work package, Actual the time actually spent. Both belong in the same timeline, visually separated – in the Gantt as two bars per row. Milestones also have a planned value (planned date) and an actual value (reached on).
Every relevant deviation is justified: in the work journal in the first person, in the timeline/planned-actual chapter in the passive voice.
First person (journal): “For ‘Docs layout’ I needed 2.5 instead of 2 hours (30 min more). The reason was a technical problem: the tables could not be transferred cleanly to InDesign.”
Passive (docs): “‘Docs layout’ required 0.5 hours more than planned. The deviation is due to a technical problem.”
Daily notes with the date, in the first person (in the Mediamatik example: 3 to max. 10 pages):
In planomatti, “Take from timeline” pre-fills the day's work packages and hours. You add the text in your own words – AI-generated sections are not allowed in the IPA.
As a guide when setting up – the template itself starts empty so your timeline fits your assignment exactly.
Mediamatiker EFZ
With target group & customer persona, creativity techniques, test users and docs layout in InDesign.
Informatiker EFZ
Inform, plan, decide, implement, check, evaluate – including test concept and test log.
Entwickler Digitales Business EFZ
Business process and requirements analysis, prototype or automation, acceptance with stakeholders.
A defined time axis, the work packages in phases, milestones and a traceable planned vs actual comparison. The IPA-Handbuch QV 2026 Mediamatik (Canton of Zurich) requires a 2- or 4-hour grid.
For Mediamatiker apprentices in the Canton of Zurich: 10 consecutive working days with a scope of 70 to 90 hours. For other professions and cantons, the rules of the respective examination board apply.
Per day: the day's work, problems, how they were solved, outside help, personal conclusion of the day, open items and time (planned/actual). The journal is written in the first person.
According to the IPA-Handbuch QV 2026 Mediamatik, yes, if the source and prompt are included in the appendix. Having whole sections of the documentation written by AI is forbidden.
Yes. Invite them as a guest with the role “Supervisor” – they see the timeline live and can comment. For the expert team there are read-only links without an account.