planomatti / Project timeline
Guide · worked example · free template
To create a project timeline, list the tasks, decide what has to happen first, estimate how long each task takes, turn those estimates into start and end dates, mark the milestones and then compare progress with the plan every week. Below is a complete, dated example: a six-week marketing campaign for a product launch.
This order works for a two-week sprint as well as a six-month project.
Write down everything that has to be done to reach the goal. Cut tasks so one person can finish each in 1 to 10 working days, and group them into phases.
For each task ask: what must be finished first? Those are your dependencies. Tasks that do not depend on each other can run in parallel.
Estimate each task in working days, name one owner, then work out start and end dates from the project start. Leave out weekends, holidays and planned absences.
Mark the moments with no duration where something is approved or delivered. Put 10 to 20 percent buffer in front of any fixed deadline.
Once a week, record what is actually done and compare it with the plan. Deal with gaps straight away, not at the end.
A small company launches a new product. Team: Maya (campaign lead), Leo (copy), Ana (design and video), Sam (landing page and ads). Work starts on Monday 13 September 2027, the campaign goes live on Tuesday 12 October and the results report is due on Friday 22 October. That is 30 working days.
| Task | Owner | Days | After | Start | End |
|---|---|---|---|---|---|
| Briefing and goals | Maya | 2 | – | Mon 13 Sep | Tue 14 Sep |
| Audience and key message | Maya | 3 | Briefing | Wed 15 Sep | Fri 17 Sep |
| Milestone: brief approved | Maya | 0 | Audience | Fri 17 Sep | Fri 17 Sep |
| Copy and content plan | Leo | 6 | Brief ok | Mon 20 Sep | Mon 27 Sep |
| Visuals and video | Ana | 8 | Brief ok | Mon 20 Sep | Wed 29 Sep |
| Landing page | Sam | 4 | Copy | Tue 28 Sep | Fri 1 Oct |
| Ads and tracking setup | Sam | 3 | Visuals, Landing page | Mon 4 Oct | Wed 6 Oct |
| Final review and fixes | Maya | 2 | Ads setup | Thu 7 Oct | Fri 8 Oct |
| Buffer | – | 2 | Review | Mon 11 Oct | Tue 12 Oct |
| Milestone: campaign live | Maya | 0 | Buffer | Tue 12 Oct | Tue 12 Oct |
| Run and optimise ads | Sam | 8 | Live | Wed 13 Oct | Fri 22 Oct |
| Milestone: results report | Maya | 0 | Run | Fri 22 Oct | Fri 22 Oct |
Brief approved on Fri 17 Sep, campaign live on Tue 12 Oct, results report on Fri 22 Oct. Two days of buffer sit right before go-live, about 10 percent of the preparation time. Adjust dates for public holidays in your country.
On Friday 24 September, day 10 of 30, Maya compares plan and reality:
| Task | Plan by 24 Sep | Actual on 24 Sep | Difference |
|---|---|---|---|
| Briefing, audience | done (5 days) | done (5 days) | 0 |
| Copy and content plan | 5 of 6 days | 5 of 6 days | 0 |
| Visuals and video | 5 of 8 days | 4 of 8 days | 1 day behind |
Visuals are a day late, but they are not on the longest chain: ads setup waits for the landing page until 1 October anyway. The slack shrinks from two days to one and the launch date holds. Maya notes it and checks again next Friday.
Had the copy been late instead, the landing page, ads and launch would all have moved. That is why it pays to know which chain is the longest.
Copy these columns into a spreadsheet, or download the template. It works for any project with dated tasks.
| Column | What goes in | Example |
|---|---|---|
| Task | A concrete piece of work, 1 to 10 days | Landing page |
| Type | Task or milestone | Task |
| Owner | One name, not a team | Sam |
| Start / end | Dates, working days only | 28 Sep / 1 Oct |
| Working days | Calculated from start and end | 4 |
| Status | To do, in progress, done | In progress |
A project timeline answers when: tasks, dates, milestones. A project plan also covers why and what: goals, scope, responsibilities and risks. For a small project, a timeline with owners is often enough. Once there is a client, a budget or several teams, write the plan first and build the timeline from it.
These features exist in planomatti today, all free.
Calendar
Pick the “Waterfall project” or “Event & campaign” template. Enter the start date, number of working days, hours per day and days off such as public holidays.
Tasks
Add them with the Phase, Work package and Milestone buttons. In the task panel, set the assignee and a due date.
Dates
Use “Paint plan” to drag planned time across the grid, or type the hours. The grid goes from 30 minutes to whole days.
Order
You set the order by placing bars one after another. planomatti does not link dependent tasks automatically.
Progress
Paint actual time, type it or use the timer. Key figures show total planned, actual so far and percent of plan; each row shows its difference.
Team
Invite as many members as you need, share a read-only link with people who have no account. Export as PDF, SVG, PNG at 300 dpi or planned vs actual as CSV.
List the tasks, set their order, estimate each task in working days, derive start and end dates from the project start, add milestones and buffer, then compare progress with the plan every week.
Tasks grouped into phases, an owner per task, start and end dates, dependencies, milestones and a buffer before fixed deadlines. Optionally the actual time spent.
The timeline is part of the project plan and shows when things happen. The project plan adds goals, scope, responsibilities and risks.
As a rule of thumb, 10 to 20 percent of the duration, more for new or uncertain work. Keep it in one block before the deadline.
Yes. The project timeline template for Excel is free and contains the example from this page.
planomatti is free, with no trial and no credit card. To create and edit a timeline you need an account with name, email and password. People who only need to view it can open a read-only link without an account.
Sign up free, choose a template and add the tasks from your list.